Supplied materials, labour and access equipment to install and commission a trace heating system to maintain a temperature of +40°C.
Wednesday 19 December 2007
Friday 14 December 2007
Wednesday 5 December 2007
Friday 30 November 2007
Thursday 29 November 2007
Monday 26 November 2007
Thursday 22 November 2007
Tuesday 20 November 2007
Monday 19 November 2007
Monday 12 November 2007
Tuesday 6 November 2007
Monday 29 October 2007
Thursday 25 October 2007
Monday 22 October 2007
Friday 19 October 2007
Thursday 18 October 2007
Wednesday 17 October 2007
Drayton House - Stourbridge
ESH were contracted to upgrade the existing leak detection control panel to a 20 zone unit and return to site to re-terminate the 16 zones and install 4 new zones monitoring oil detectors, located under the oil feed pipe line and around the final connection to the boiler.
ESH were contracted to upgrade the existing leak detection control panel to a 20 zone unit and return to site to re-terminate the 16 zones and install 4 new zones monitoring oil detectors, located under the oil feed pipe line and around the final connection to the boiler.
Tuesday 16 October 2007
Monday 15 October 2007
Friday 5 October 2007
Wednesday 3 October 2007
Walsall Manor Hospital
For this project ESH supplied materials and labour to install and commission the trace heating system to maintain the DHWS pipework at +55°C, together with a temperature controller to purge the system once a week a +65°C. This project required 400m of type H2OWAT65 self limiting heating tape.
For this project ESH supplied materials and labour to install and commission the trace heating system to maintain the DHWS pipework at +55°C, together with a temperature controller to purge the system once a week a +65°C. This project required 400m of type H2OWAT65 self limiting heating tape.
Thursday 27 September 2007
Monday 24 September 2007
Thursday 20 September 2007
Monday 17 September 2007
Thursday 13 September 2007
Avonmouth WWTW
Supplied and installed frost protection trace heating to steel, stainless and plastic pipework in the following areas:
Supplied and installed frost protection trace heating to steel, stainless and plastic pipework in the following areas:
- 170m of digester feed pipework
- 80m of stainless/ductile pipework from tank to gravity feed thickener units
- 49m of plastic pipework to GFT units
- 65m of sludge feed pipes to 3 mono pumps
- 137m of washwater pipe from pump area to GFT area
- 50m of hydrant washwater pipework
- 12m of galvanised drain pipework
Friday 7 September 2007
Thursday 6 September 2007
Monday 3 September 2007
Tuesday 28 August 2007
Friday 24 August 2007
HSBC National Data Centre - Bootle
The scope of this project was to design, supply, install and commission a leak detection system to monitor the flow and return chilled water pipework within the floor void of the data hall in phase 3 building. Also within the phase 3 building ESH were contracted to frost protect 63m of foam suppression pipework.
The scope of this project was to design, supply, install and commission a leak detection system to monitor the flow and return chilled water pipework within the floor void of the data hall in phase 3 building. Also within the phase 3 building ESH were contracted to frost protect 63m of foam suppression pipework.
Wednesday 22 August 2007
Tuesday 21 August 2007
Monday 20 August 2007
Friday 17 August 2007
Reckitt Beckniser Ltd - Derby
To supply and install 240 volt trace heating to temperature maintain pipework and a tank at +30°C. Section one comprised of one tank plus the associated pipework, all in a safe area - Section two comprised of pipework only associated with another tank, which was situated in a Zone 1 Temperature Class T3 Gas Group 2B.
To supply and install 240 volt trace heating to temperature maintain pipework and a tank at +30°C. Section one comprised of one tank plus the associated pipework, all in a safe area - Section two comprised of pipework only associated with another tank, which was situated in a Zone 1 Temperature Class T3 Gas Group 2B.
Tuesday 14 August 2007
Monday 6 August 2007
Friday 3 August 2007
Thursday 2 August 2007
Wednesday 1 August 2007
Monday 30 July 2007
Alstom Power Ltd - Rugby
Supplied and installed trace heating and thermal insulation to temperature maintain a VDR vapour storage vessel and its associated pipework. The 100mm NB suction pipework needed to maintain a temperature of +15°C whilst the remainder, including the vessel, needed to maintain +25°C to prevent condensation.
Supplied and installed trace heating and thermal insulation to temperature maintain a VDR vapour storage vessel and its associated pipework. The 100mm NB suction pipework needed to maintain a temperature of +15°C whilst the remainder, including the vessel, needed to maintain +25°C to prevent condensation.
Friday 27 July 2007
Wednesday 25 July 2007
Monday 23 July 2007
Wednesday 18 July 2007
Monday 16 July 2007
Wednesday 11 July 2007
Monday 9 July 2007
Thursday 5 July 2007
Tuesday 3 July 2007
Monday 2 July 2007
Tuesday 26 June 2007
Friday 22 June 2007
Wednesday 20 June 2007
Monday 11 June 2007
Monday 4 June 2007
Monday 28 May 2007
Thursday 24 May 2007
Monday 21 May 2007
Monday 14 May 2007
Thursday 10 May 2007
Tuesday 8 May 2007
Friday 4 May 2007
Monday 16 April 2007
Friday 13 April 2007
Wednesday 11 April 2007
Thursday 5 April 2007
Monday 2 April 2007
Monday 26 March 2007
Wednesday 21 March 2007
Monday 12 March 2007
Tuesday 6 March 2007
Friday 2 March 2007
Wednesday 28 February 2007
Monday 26 February 2007
Friday 23 February 2007
Thursday 22 February 2007
Tuesday 20 February 2007
Friday 16 February 2007
Tuesday 13 February 2007
Tuesday 6 February 2007
Friday 2 February 2007
Thursday 1 February 2007
Thursday 25 January 2007
Tuesday 23 January 2007
Monday 22 January 2007
Thursday 18 January 2007
Monday 15 January 2007
Friday 12 January 2007
Thursday 11 January 2007
Monday 8 January 2007
Thursday 4 January 2007
Subscribe to: