Avonmouth WWTW
Supplied and installed frost protection trace heating to steel, stainless and plastic pipework in the following areas: 

  • 170m of digester feed pipework
  • 80m of stainless/ductile pipework from tank to gravity feed thickener units
  • 49m of plastic pipework to GFT units
  • 65m of sludge feed pipes to 3 mono pumps
  • 137m of washwater pipe from pump area to GFT area
  • 50m of hydrant washwater pipework
  • 12m of galvanised drain pipework