CPS Fuels Ltd - Norwich
Supplied and installed trace heating tape, installation and cladding to maintain +15°C in a Zone 1 Hazardous Area Gas Group IIB temp Class T3.

Monday 26 February 2007

Cotts Beverages - Kegworth
This project involved trace heating of Glucose pipework and tank. The tank was 4.3m tall, 3.5m diameter with approximately 15m of pipework, which all needed to be maintained at 50°C.

Friday 23 February 2007

New Romney WWTW - Kent
Supplied, installed and commissioned the trace heating systems to provide frost protection on the following circuits - Anion units, waste water tank, salt saturation & recovered rinse water tank pipelines.

Thursday 22 February 2007

Quarry Hill WWTW - Carlisle
ESH were contracted to go back to Quarry Hill WWTW to supply and install trace heating, lagging and cladding to frost protect 3 tanker points.

Tuesday 20 February 2007

Moy Park Ltd - Sleaford 
ESH supplied and installed VC constant wattage heating tape to provide frost protection for this large producer of organic and free range poultry.

Friday 16 February 2007

Cardinal Place - London
Supplied H2OWAT55 self limiting heating tape to this retail and office development project.

Tuesday 13 February 2007

Bowmer & Kirkland Ltd - Rotherham
Supply materials and labour to install and commission trace heating to frost protect 2 large carrier units and one small unit. 

Tuesday 6 February 2007

Park Plaza Hotel - Cardiff
Supplied ESRS self regulating heating tape for installation within the hotels health club.

Friday 2 February 2007

Tesco Store - Trowbridge
ESH supplied ESRS self regulating heating tape to be installed within the above site.

Thursday 1 February 2007

Quarry Hill WWTW - Carlisle
For this project we supplied the materials and labour to install and commission the trace heating tape, lagging and cladding to 3 connections attached to a large GRP tank to provide frost protection.