Tuesday, 28 August 2007

Russells Hall Hospital - Dudley
Supplied and installed an additional 40m of FBTBOJ self regulating heating tape to provide frost protection to the CHW pipework.

Friday, 24 August 2007

HSBC National Data Centre - Bootle
The scope of this project was to design, supply, install and commission a leak detection system to monitor the flow and return chilled water pipework within the floor void of the data hall in phase 3 building. Also within the phase 3 building ESH were contracted to frost protect 63m of foam suppression pipework.

Wednesday, 22 August 2007

Cotton Valley WTW - Milton Keynes 
ESH supplied and installed frost protection trace heating to approximately 63m of 1" and 2" water pipework associated with 6 vessels.

Tuesday, 21 August 2007

Atlas Quarry Works - Batley
Supplied and installed a trace heating system to a large industrial dust hopper. The hopper needed to maintain a temperature of +50°C.

Monday, 20 August 2007

Andrew Corporation - USA
Another large order from this American communications giant. ESH supplied and designed 96 x 3.7 dish heater panels heater panels designed to fit to the rear of Satellite Receiving Dish Aerials to prevent ice formation.

Friday, 17 August 2007

Reckitt Beckniser Ltd - Derby
To supply and install 240 volt trace heating to temperature maintain pipework and a tank at +30°C. Section one comprised of one tank plus the associated pipework, all in a safe area - Section two comprised of pipework only associated with another tank, which was situated in a Zone 1 Temperature Class T3 Gas Group 2B.

Tuesday, 14 August 2007

Lancaster Audi Showroom
Supplied materials and labour to install and commission the trace heating system to provide frost protection to 55m of 40mm Ø plastic pipework.